山东无尘车间彩钢板施工工艺您了解吗?

来源:http://www.henganjh.cn │ 发表时间:2019-07-15 

  根据无尘车间的特点,结合项目的实际情况,符合相关标准和规范,根据特定的无尘车间工作与工程设计图纸的要求,制定具体的施工程序和进度无尘车间项目,按部就班,逐步保证车间施工质量和无尘条件下满足业主进度要求,顺利完成洁净室施工。今天山东无尘车间公司为您传授彩钢板材施工技术。
  According to the characteristics of dust-free workshop, combined with the actual situation of the project, in accordance with the relevant standards and norms, and according to the requirements of specific dust-free workshop work and engineering design drawings, specific construction procedures and progress of dust-free workshop projects are formulated, and work on schedule, gradually ensuring the construction quality of workshop and meeting the owner's progress requirements under dust-free conditions, and smoothly. Complete clean room construction. Today, Shandong Dustless Workshop Company teaches you the construction technology of color steel sheet.
  山东无尘车间主要项目施工流程:
  Construction process of main projects of dust-free workshop in Shandong Province:
  制定测量→在无尘车间地板平整处理→实验排气管安装→安装外壳结构在无尘车间→安装天花板在无尘车间→建设PVC地板在无尘车间→安装实验装置→安装通风设备和tuyway→设备调试→全系统测试
  Establishment of measurement floor leveling treatment in dust-free workshop installation of experimental exhaust pipe installation of shell structure in dust-free workshop installation of ceiling in dust-free workshop construction of PVC floor in dust-free workshop installation of experimental equipment installation of ventilation equipment and tuyway equipment debugging whole system testing
  注:山东无尘车间施工应在土建工程竣工及现场清理后进行。
  Note: Construction of dust-free workshop in Shandong should be carried out after completion of civil engineering and site cleaning.
  一、彩钢板的施工:
  1. Construction of coloured steel plates:
  在实际施工过程中,天花板和墙板安装好后,必须同时进行撕膜、清洗和上胶。一般彩钢板撕膜前,应全面检查室内施工的各种专业,包括空调的安装、各种管道的安装、门窗的安装及相关技术设施的施工,以满足要求,并做好检查记录。
  In the actual construction process, after the ceilings and wallboards are installed, film tearing, cleaning and gluing must be carried out at the same time. Before tearing film of color steel plate, all kinds of specialties of indoor construction should be checked comprehensively, including installation of air conditioning, installation of various pipes, installation of doors and windows and construction of related technical facilities, in order to meet the requirements and make good inspection records.
  二、吊顶吊件生产安装:
  2. Production and installation of ceiling lifting parts:
  1. 确定吊架和楼板的吊点。
  1. Determine the hanging point of the hanger and floor.
  2、根据确定的所有吊点,计算所用吊架的尺寸,根据吊点之间的距离,确定主龙骨的类型,确保吊顶荷载满足规范要求。
  2. Calculate the size of the suspension frame according to all the suspension points, and determine the type of the main keel according to the distance between the suspension points, so as to ensure that the load of the suspension roof meets the requirements of the code.
  3、衣架、主龙骨加工生产。
  3. Clothes hanger and main keel processing and production.
  4、吊架、主龙骨、t型铝龙骨安装。
  4. Installation of hanger, main keel and T-type aluminium keel.
  5、严格控制吊架与地面的连接,确保主龙骨与t龙骨安装垂直、不脱落。
山东无尘车间
  5. Strictly control the connection between the hanger and the ground to ensure that the main keel and the T keel are installed vertically and do not fall off.
  三、彩钢板安装:
  III. Installation of coloured steel plates:
  1、彩钢板的生产是在工厂进行的,通过先进的生产工艺控制,高质量的保证。
  1. The production of coloured steel plate is carried out in the factory. It is guaranteed by advanced production process control and high quality.
  2. 施工方法
  2. Construction method
  就位准备:彩钢板为预制楼板,可短不可长,可窄不可宽。形成一个大的块,一个活的。只有保证每块板的准确位置,才能保证所有板的安装质量和零件的安装质量。
  In-place preparation: coloured steel plate is prefabricated floor, which can be short or not long, narrow or not wide. Form a big block, a live one. Only by ensuring the exact position of each board can the installation quality of all boards and parts be guaranteed.
  连接可靠:彩钢板与天花板龙骨连接,板材与板材连接,板材与配件连接是保证板材使用安全的主要环节,必须认真完成每一点的连接,确保整体的可靠性。
  Reliable connection: color steel plate and ceiling keel connection, plate and plate connection, plate and fittings connection is the main link to ensure the safety of plate use, we must conscientiously complete the connection of each point to ensure the overall reliability.
  密封性和密封性:天花板由板组成,必须保证搭接接头在两个方向都是紧固的,接头和外露接头可靠且至关重要,只有保证每条线、每一点的密封性良好,才能保证整体质量。
  Sealability and Sealability: The ceiling is composed of boards. It is necessary to ensure that the lap joints are tightened in both directions. The reliability and importance of the joints and the exposed joints can only be ensured if the sealing of each line and point is good.
  工程配合:为保证整个项目的进度,配合吊顶开闭。
  Engineering cooperation: In order to ensure the progress of the whole project, cooperate with the opening and closing of the ceiling.
  四、墙板安装:
  4. Wallboard Installation:
  1. 板材的生产和天花板的生产是一样的。根据施工图计算出所有墙板的尺寸和砌块数量,并提前在工厂加工,以便以后使用。当条件成熟时,他们将立即被运到现场。
  1. The production of sheet metal is the same as that of ceiling. According to the construction drawings, the sizes of all wallboards and the number of blocks are calculated and processed in advance in the factory for later use. When conditions are ripe, they will be transported to the scene immediately.
  2. 仔细阅读图纸,确定墙板的位置。
  2. Read the drawings carefully and locate the wallboard.
  3.按照图纸安装50*25铝地槽,并使用8*75膨胀螺丝将铝地槽连接到地面。
  3. Install 50*25 aluminium groove according to the drawing and connect the aluminium groove to the ground with 8*75 expansion screw.
  4、板材就位,板材与板材连接要求平整,板材接缝紧密。按线路线路,将线路管道埋入,开孔。
  4. The plate should be in place, the connection between the plate and the plate should be smooth, and the joint of the plate should be close. According to the line, bury the line pipeline and open the hole.
  5. 安装铝配件。在墙面与天花板、墙面与地面、墙面之间的角处安装弧铝材料,确保墙面无死角,表面无螺钉。铝管件和板的接头用三种胶水密封。
  5. Install aluminium accessories. Arc aluminium material is installed at the corner between wall and ceiling, wall and ground, wall to ensure that there is no dead corner and no screw on the surface. The joints of aluminium pipes and plates are sealed with three kinds of glue.
  安装门窗
  install doors and windows
  根据门的尺寸提前准备好材料。根据现场图纸尺寸安装。门窗配件要求缝缝准确,墙角要保证垂直度,密封可靠,减少门窗配件之间的缝隙。
  Material is prepared in advance according to the size of the door. Install according to the size of field drawings. Door and window fittings require accurate seam, wall angle to ensure verticality, reliable sealing, reduce the gap between door and window fittings.
  以上文章内容都是山东无尘车间公司今天为您介绍的文章内容,相信您已经理解了,所以今天我们就不多说了,希望这篇文章能对您有所帮助。想要了解更多内容,欢迎访问网站:http://www.henganjh.cn
  The above articles are all the articles introduced by Shandong Dust-free Workshop Company for you today. I believe you have understood them. So we won't say much today. I hope this article can be helpful to you.